Traffic Signal Synchronization

Project Description:

This project will develop and maintain improved multi-jurisdictional signal synchronization timing based on current travel patterns. The project will include the installation of a new central software system, upgraded controller hardware and firmware, and signal cabinet replacement. Funding will be provided by Measure M2, local match, and other agencies. 

Aliso Creek Road:

  • Budget: $115,215 (City Match, AQMD) and $460,860 (Grant Funding)
  • Location: Aliso Creek Rd. from Moulton Pkwy. to El Toro Rd. (21 total intersections, 5 in Laguna Niguel)
  • Partner Agency: Aliso Viejo
  • Anticipated Start Date: March 2021

aliso creek traffic synchronization


Alicia Parkway:

  • Budget: $220,900 (City Match, AQMD) and $883,238 (Grant Funding)
  • Location: Alicia Pkwy. from Crown Valley Pkwy. to Rustic Oak (40 total intersections, 12 in Laguna Niguel)
  • Status: New timing implemented. Staff is maintaining timing with OCTA Lead.
  • Percent Complete: Construction portion is 100% complete. Operations and maintenance portion is anticipated to be completed by February 2022. 

Alicia pkwy traffic synchronization