Accessible Pedestrian Signal Push Buttons

Project Description:

This project provides ADA compliant accessible facilities at 6 intersections along various arterials, including Alicia Parkway, La Paz Road, Crown Valley Parkway, and Golden Lantern. This project replaced traditional push buttons with vibro-tactile buttons, as well as a customizable audio broadcast of messages and sounds for sight-impaired pedestrians.  

Project Schedule: 

  • Award of Construction Contract: October 2022
  • Start of Construction: October 2022
  • Construction Complete: April 2023
  • Current Status: Construction is 70% complete. 

Project Funding:

  • FY 21-22: $50,000 (CDBG)

The proposed locations for Fiscal Year 2021-2022 are shown in the map below: 

2021-2022 six proposed locations for Accessible Pedestrian Signal Push Buttons