Paseo De Colinas Groundwater Seepage Repairs

Project Description:

This project includes the installation of underground drainage and connection to the storm drain on Paseo de Colinas, north of Cabot Road. This drainage project will remediate underground water from surfacing along Paseo de Colinas. To address seasonal presence of surface water, an underground drain will be installed and connected to the storm drain system. 

Project Schedule:

  • Award of Construction Contract: January 2021
  • Start of Construction: March 2021
  • Completion of Construction: July 2021

Project Funding:

  • Fiscal Year 2020-2021: $350,000 (Measure M2)

Current Status:

The contractor, CHI Construction, will be excavating and installing the pipes on eastbound Paseo de Colinas beginning the week of April 26th.  Please be aware that the contractor will be closing one travel lane on eastbound Paseo de Colinas west of Cabot Road to safely perform the work. Delays should be expected when traveling in the work area. Motorists are encouraged to use alternate routes.

This page will be actively updated to share the current status of the project.