Chapparosa Park Playground Replacement

The Chapparosa Pak Playground Replacement Project includes the replacement of the playground equipment and the installation of a rubberized play surface, monument sign, benches, trash receptacles, and picnic shelters that will add shade at Chapparosa Park. 

The project's design phase was completed in Fiscal Year 2019-20, but construction was halted due to the COVID-19 pandemic. Because this project was delayed, it is eligible for the use of American Rescue Plan funds. 

The project will be completed in Fiscal Year 2021-22 and is on the Park and Recreation Commission's prioritized playground replacement plan. The City will be advertising bids and awarding a contract in the Fall and Winter 2021. Construction is expected to begin in Spring 2022, and the project will be completed in Summer 2022.

Project Schedule: 

  • PS&E and Bid: October 2021
  • Start of Construction: January 2021
  • Completion of Construction: June 2022
  • Current Phase: Construction
  • Current Status: Project Advertised for Bids

This page will be actively updated to share the current status of the project. For any questions, please contact the Project Manager JC Herrera at (949) 362-4382.